Meeting Date File
March 9, 2018

228. Report on magnet ripple corrections in the SPS

March 2, 2018

227. INTC report, ELENA status and planning, Magnet earthing in the injector chain, Update on the injector schedule, Status of Injector Kicker in AD, Crab Cavities activities status update

February 16, 2018

226. Crab Cavities test stand, installation status, Report on possibility to recover LIU related RF commissioning for PS, Follow-up of the SPS LSS2 slow extraction losses and induced radioactivity in 2017, Status of the ELENA e-cooler leak detection

February 9, 2018

225. Report on the 1st part of the BE-OP Linac4 reliability run and plans for the 2nd part, Report on the SPSC of 23-24 January, ELENA e-cooler issues: status, mitigation plans & impact on schedule, MD endorsement, MD plans for the BDF in T6 of TDC2, Feedback from the Evacuation drill in SPS

January 19, 2018

224. Summary of the 2017 slow extraction workshop, Status of AD stochastic cooling amplifiers

January 12, 2018

223.PS and TT2 schedule during YETS, Draft 2018 Injectors Schedule, PS RF system start-up in 2018, MD requirements and plans for 2018,Status report on the Control Change Requests.

December 8, 2017

222. MTE with high intensity and future of CT, Update on LINAC4 reliability run, Refurbishment of the PS complex layout and integration drawings, Assessment of EHN1/EHN false floors

November 3, 2017

219. Report from RP survey with robot in SPS, SPSC report, Outcome of the SPS safety project review, Update on Linac2 decommissioning

October 20, 2017

218. Future PS & TT2 Cooling System

October 6, 2017

217. ITS3 debriefing, New coordination map for injectors, ELENA status progress

September 22, 2017

216. BAs flooding issues and their mitigation, REX Isolde RF improvement, results and consolidation plans, Report on LINAC3 amplifier failure, Mandate for AD and ISOLDE technical coordinators

September 15, 2017

215. aC coating in the YETS, Isolde: plans and status for Module 4, Isolde radiation issues with 94Rb beams

September 1, 2017

214. Cooling issues in the NA, Consolidation of the AD ring quadrupoles, Report from EACM on LS2 activities, Crab Cavity Operational Scenario, Update on Gbar readiness for beam permit

August 18, 2017

213. Update on the injector TS, 2017 schedule update: possible extension of 2 weeks in ISOLDE, n_TOF, EA

August 11, 2017

212. ISOLDE High Voltage power converter consolidation plans, Report on the recent SPS dump kicker trigger issues and mitigation plans, Update on the injector TS

August 4, 2017

211. INTC report n_TOF, INTC report ISOLDE, Update on the availability of the MORPURGO magnet, Injector technical stop

July 21, 2017

210. SPS access system upgrade in LS2. Report of International Advisory Panel of the HIE-ISOLDE project. TIDVG#3 post mortem leak detection. Access system in b. 361.

July 14, 2017

209. EYETS coordination post-mortem. Summary of the International Review on PS Powering Strategy. Plans for tests on SPS crystal extraction and on other potential extraction loss reduction measures. Consolidation of the Linac3 HLRF system. SPS ZS tank 2 alignment issues: solution to the losses.

July 7, 2017

208. Non-LHC beam performances afer Linac4 connection, Status and future prospects of distributed optical fibre radiation and temperature sensing at CERN, Update on the master schedule of YETS 2017/18, Reliability run Linac4

June 23, 2017

207. North area cooling and other specific topics, Report from the SPSC, New functional specification for impedance Shielding of new SPS Sector Valves


You are here